PORTFOLIO

Unilever Project 60 Home and Personal Care Facility

On the roof of an existing 300,000 SF Unilever facility, 11 20-ton air handling units were installed and 15 exhaust fans, nine supply fans and one makeup air unit were removed.

To take on the additional 10,000-pound load from the air handling units, the existing joist and girder were reinforced. Reinforcement was completed throughout the facility during normal operations with the use of fire-resistant reinforced poly.

The work required a 600-ton, all terrain, mobile crane with a maximum jib radius at 290 feet over the facility.

Industrial Industry Excellence Coordinator: Michael Ernst | | 410.821.1100