Madeira Waste Water Treatment Plant

Construction of an 18,000 SF wastewater treatment plant and pre-engineered metal control building. The new facility replaces an existing plant which was demolished upon completion of the new facility. The new system uses extended aeration for its treatment process. The plant consists of 16 buried precast tanks, a mechanical screen chamber, UV disinfection channel, pumps, generator, a 1,200 LF of four-inch force main and a 600 LF of eight-inch outfall pipe.

Water Industry Excellence Coordinator: Chris Collins | | 410.337.6911